Step 1-
Research
Thank you for taking the time to learn about the Building
Design Process. After reading this section, we know that you’ll
have a better understanding of each step of the design process. We
look forward to being a part of your project.

Phase One: Research
Before Greenwood & Moore, Inc. (G&M)
can perform any design work on your project, we must perform research
to identify the specific development requirements for your
project. Most municipalities throughout the state have similar
approval processes, but the specific development requirements can
change substantially from one city/county to the next. This is why it
is vitally important that we research the specific development
requirements for your particular project.
When performing research for a project,
G&M will contact some or all of the following agencies,
depending upon the scope and location of the project.
|
• |
Planning/Zoning
Department |
|
• |
Building Department |
|
• |
Fire Department |
|
• |
Public Works Department |
|
• |
Health Department |
|
• |
Department of Fish & Game |
|
• |
Army Corps of Engineers |
|
• |
California Department of
Transportation (Cal Trans) |
|
• |
California Costal Commission |
The first four departments
commonly have input into most small residential projects. The
remaining five departments typically have input in only very
special circumstances.
For more information about the research phase, please continue
reading below or move on to
Step
2 of the residential process.

The following information is a short overview of the functions
performed by the departments listed above:

Planning/Zoning Department:
The Planning/Zoning department is the local government agency
(city or county) that is responsible for determining and
regulating land use in their jurisdiction. Local “design rules”
come from the Planning Department so it is usually the first
agency contacted.
For G&M to provide effective
research, you should at least have a detailed description of the
proposed project and an Assessor’s Parcel Number (APN) for the
property. The APN can be found on an existing deed or it can also
be found on existing property tax records. If you can’t find the
APN, the Planning Department can look it up for you.
Building Department
The Building Department administers and enforces the appropriate
building codes. In general, the local building department is
responsible for:
 |
Reviewing and approving any
drawings or calculations associated with a project. |
 |
Performing building
inspections during the course of construction |
 |
Identifying and correcting
building code violations. |
Fire Department
The Fire Department enforces fire prevention ordinances for
construction projects in their local jurisdiction. For most simple
residential projects there will little or no special construction
requirements issued by the local Fire Department. Significant,
high-cost Fire Department construction requirements are more
commonly associated with larger projects such as new homes or very
large room additions. However, proper research by
G&M eliminates any surprises
associated with this issue.
Public Works Department
The local Public Works Department is typically responsible for the
construction, development and maintenance of facilities that are
located in the public right-of-way such as streets, roads,
bridges, sidewalks, sewer systems and storm drains.
For most simple residential projects there will little or no
special construction requirements issued by the local Public Works
Department. Significant Public Works Department construction
requirements are more commonly associated with larger projects
such as new homes or very large room additions.
Depending upon the location of a property and the scope of the
proposed construction or remodeling project, it may be possible
that certain unusual State and Federal agencies may also need to
be contacted during the research phase. Some of these agencies
are:
|
• |
Health Department
The Health Department works to preserve the health and well
being of communities. G&M
contacts the Health Department if a property is located in a
less developed rural area because it is possible that a public
sewer or water system does not service the property, thus
requiring a septic system. G&M
researches the capacity requirements of these systems in
relation to the size of the project to determine if the
project is feasible in its current iteration.
In most highly developed urban areas, a homeowner will not
need to contact the local Health Department as part of the
project review process.
|
|
• |
U.S. Department of Fish &
Game:
The U.S. Department of Fish & Game is primarily concerned with
the impact that a development will have on local wildlife.
Approval may be required when performing work in or near
wetlands or a natural watercourse. If a property is located
near a dry streambed, the U.S. Department of Fish & Game may
have the property classified as a watercourse! This
designation could have a major impact on the proposed design
or even prohibit the project.
|
|
• |
U.S. Army Corps of
Engineers:
The U.S. Army Corps of Engineers is typically involved with
any construction that occurs in or near oceans, rivers and
wetlands. They often work hand in hand with the U.S.
Department of Fish & Game. Because the U.S. Army Corps of
Engineers is primarily concerned with the impact that a
development will have on water flow and soil erosion,
developments located in known flood plains will typically
require their approval.
|
|
• |
California Department of
Transportation (CALTRANS)
If a project is adjacent to a State Highway and work is to be
performed in the public right-of-way, then it will be
necessary to obtain approval from the State agency responsible
for the highway (in California this agency is CALTRANS).
The approval process from CALTRANS can add 4-6 weeks onto the
permit timeframe. Therefore, you will want to submit for this
approval at the same time that you submit for the regular
building permit.
|
|
• |
California Coastal
Commission
If a project is located on, or very near to, a coastline, then
it may be necessary to obtain approval from the State agency
responsible for coastal development. The approval process for
this type of approval can add 4-6 months onto the permit
timeframe. Typically, you will need to have this approval
before you can submit for a building permit.
 |
|